Noise Reduction - ATCO Noise Management Noise Suppression and acoustical consultants
Noise Pollution - Corporate Commitment Industrial Noise Control - Careers Acoustic Solution - ATCO Group
Noise Mitigation - ATCO Logo
Home Search for Noise Control Information Site Map Contact Acoustical Consulting Experts Higgott-Kane, A Division of ATCO Noise Management
Noise Abatement - ATCO Logo
Acoustic Consulting- Profile Suppression System -  Products & Services Acoustic Barriers - Industry Solutions Noise Reduction - Project Library Noise Pollution - Media Room Acoustical Engineering - Industry Events
Noise Abatement
Industrial Noise Control Examples Industrial Noise Control Success Stories  
Noise Control for Power Generation
Noise Control for Oil and Gas
Noise Control for Industrial Gas Production
Noise Control for Petrochemical
Noise Control for Original Equipment Manufacturers
Noise Control for Retrofit
Noise Control for Light Rail Transit (LRT)
Noise Control for Other Noisy Industries

Florida Light & Power
Design, supply and erection of acoustical steam turbine generator building.

Name:
Manatee Power Plant Expansion Project
East of Parrish, Florida, USA

Owner:
Florida Light & Power
700 Universe Blvd.
P.O. Box 140000
Juno Beach, Florida
USA 33408

Customer:
Black & Veatch
11401 Lamar Avenue
Overland Park, Kansas
USA 66211

Reference:
Doug Traphagen
Tel: (941) 776-0026

Description :
Owned by FPL Group, and operated by Florida Light & Power, the Manatee Power Plant was originally established in the 1970s. At the time, planners set aside a 9,500 acre site to provide for expansion purposes.

Initiated in 2003 by Florida Light & Power, the $600 million Manatee Power Plant addition is one component of a larger expansion plan. The Manatee Phase 1 expansion, completed in mid-2005, added a new natural gas-fired 1100 megawatt combined-cycle generating unit.

Noise Source :
Toshiba Steam Generator Unit

Performance Targets :
The far field target was 60 dBA at 122 meters in all directions. Sound pressure levels were not to exceed 85 dBA at 3 ft from the enclosure and 5 ft above pedestal level.

<< back to Power Generation Index
<< Download pdf here

Manatee Power Plant Expansion Project

 

Manatee Power Plant Expansion Project

 

Project Challenges :
The building was erected on the steam turbine pedestal which is 40 ft above grade. During construction, four hurricanes reached the plant site, stopping work and refocusing Florida labor on clean-up and restoration.

Status :
The project was completed over five months during 2004 and 2005.