Noise Reduction - ATCO Noise Management Noise Suppression and acoustical consultants
Noise Pollution - Corporate Commitment Industrial Noise Control - Careers Acoustic Solution - ATCO Group
Noise Mitigation - ATCO Logo
Home Search for Noise Control Information Site Map Contact Acoustical Consulting Experts Higgott-Kane, A Division of ATCO Noise Management
Noise Abatement - ATCO Logo
Acoustic Consulting- Profile Suppression System -  Products & Services Acoustic Barriers - Industry Solutions Noise Reduction - Project Library Noise Pollution - Media Room Acoustical Engineering - Industry Events
Noise Abatement Projects
Industrial Noise Control Examples Industrial Noise Control Success Stories  
Noise Control for Power Generation
Noise Control for Oil and Gas
Noise Control for Industrial Gas Production
Noise Control for Petrochemical
Noise Control for Original Equipment Manufacturers
Noise Control for Retrofit
Noise Control for Light Rail Transit (LRT)
Noise Control for Other Noisy Industries

Proctor & Gamble do Brazil
Manufacturing Plant

Description:
The Louveira Manufacturing Plant produces a diversity of personal care and beauty products, including diapers and shampoo.  The plant is located outside the town of Louveira in São Paulo State but close to a small village.

Customer:
Proctor & Gamble do Brazil

Scope of Work: 
To assist Proctor & Gamble respond to noise complaints from residents of a nearby village located just outside the town of Louveira, and to successfully meet legal requirements, ATCO was contracted to undertake three separate activities:

  • Implement two acoustical surveys;
  • Design preliminary noise mitigation solutions, designed to meet a legal compliance level of 50 dB(A) in the nearby residential area;
  • Provide budget pricing

The project was completed within a four-month time period between November 2003 and February 2004.

Project Location:
Louveira, São Paulo, Brazil

Noise Sources:
Through its acousticalal surveys, ATCO identified a variety of noise sources, including nine process fans, six air compressors, four cooling towers and the building's ventilation systems.

Performance Targets:
The plant is located near a small village outside the town of Louveira, and is in close proximity to a motel, located approximately 545 feet (166 meters) away.  The legal compliance level of 50 dB(A) was chosen as the target at the site of the motel.

Silencing Solutions:
ATCO designed, supplied and installed its proprietary acoustical assemblies for the walls, roof, acoustical doors, silencers and barrier walls.

<< back to Petrochemical Index
<< Download pdf here

 

Noise survey and acoustic assemblies for Proctor and Gamble Manufacturing Plant